Most booth cost overruns don't come from the design or the materials: they come from deciding late. Workshop rush jobs, express freight, reprinted graphics. Planning ahead is, quite literally, the cheapest way to get a better booth.

This is the timeline we recommend. Durations vary with the size and complexity of the project, but the order doesn't change.

Stage 1 · Brief and budget

When: as soon as you confirm your space at the show.

Stage 2 · Design and render

With a clear brief, the design team proposes the concept in 3D. Layout, materials, graphics and lighting are defined here. This is the time to make changes: in a render they're cheap, in the workshop they're not.

Stage 3 · Approval and final artwork

The stage where the most time gets lost. To avoid it:

Stage 4 · Fabrication

Woodworking, metal, painting, printing and lighting move forward in parallel. The more complete the approved design, the fewer surprises. When possible, we do a test assembly in the workshop to check joints, graphics and lights before heading to the venue.

Stage 5 · Logistics and setup

Transport, staff access permits, the electrical connection contracted with the organizer and setup within the assigned window. This step depends on each venue's rules, which is why it's worth reviewing them from stage 1.

Stage 6 · Event, teardown and storage

During the event, keep a technical contact on hand for adjustments. At closing: teardown, removal and, if the booth is reusable, an inventory of parts and storage for the next show.

What helps most: booking production time as soon as you confirm the show. Event seasons fill up and workshops work first come, first served.